Missouri Slope road work: Nov. 13 to 22: Apple Creek Road reopens, Tyler Parkway still closed

Apple Creek Road is open again east of Bismarck. Tyler Parkway and Cogburn Road stay closed through Nov. 27, westbound East Bismarck Expressway is down to one lane through Nov. 20, and First Street NW in Mandan is set to finish Nov. 25.

Map of Bismarck and Mandan with six numbered pins marking road work for Nov. 13 to 22, 2026, including First Street NW in Mandan, Main Avenue and Airport Road, and East Bismarck Expressway.

Friday, Nov. 13, through Sunday, Nov. 22, 2026

Apple Creek Road east of Bismarck is open again at its rebuilt bridge, with only seeding and cleanup left. In northwest Bismarck, the Tyler Parkway and Cogburn Road intersection stays closed with a posted detour through Nov. 27, and westbound East Bismarck Expressway is down to one lane near Railroad Avenue through Friday, Nov. 20, for water inlet repairs.

Interstate 94

Bismarck to Menoken

I-94 between the east Bismarck interchange and Menoken no longer has a work zone listed on ND Roads. Last week the reconstruction listing for mileposts 162.36 to 172.126 ran through Nov. 20, with all lanes open. The westbound Apple Creek Rest Area, about eight miles east of Bismarck, reopened Monday, Nov. 9, after building upgrades, NDDOT said.

Mandan and Morton County

Memorial Highway and Main Street, Mandan

Main Street and Memorial Highway/Mandan Avenue now has two left-turn lanes from eastbound Mandan Avenue and from westbound Memorial Highway onto Main Street, a change that was set to open as early as Nov. 3, NDDOT said. Five lanes are to stay open at normal speeds through the winter once this season's work wraps up. The Oct. 23 project newsletter says stormwater work near 3rd Street SE continues through November and is not expected to affect traffic. No newer update is posted on the city's project page. Questions go to the project hotline, 701-667-1033.

First Street NW, downtown Mandan

First Street NW, between Sixth and Fourth avenues NW, remains under construction, with Main Street as the primary detour and Second Street as the secondary one, according to the city's Nov. 2 project newsletter, the newest posted. That newsletter set completion for Wednesday, Nov. 25.

N.D. Highway 1806 bridges north of Cannonball

Bismarck, Lincoln and Burleigh County

Apple Creek Road bridge

Apple Creek Road reopened to traffic after striping was finished Wednesday, Nov. 11, the Burleigh County Highway Department said. Paving was completed Nov. 9. Seeding, punch list items and final cleanup were scheduled for Friday, Nov. 13, with flagging as needed, so watch for crews near the bridge. The county posted a map of the area. Contact: Casey Einrem, 701-204-7748.

Bismarck streets

132nd Street NE bridge

The bridge on 132nd Street NE, about 1 3/4 miles north of 201st Avenue NE, remains restricted to 7 tons gross vehicle weight and 12 feet wide until further notice, the county said in February.

Done: In Bismarck, North Washington Street near West Owens Avenue, closed to through traffic for water line repairs, was listed through Nov. 6. In Burleigh County, Apple Creek Road is open again.

Later: First Street NW in Mandan is set to finish Nov. 25, and the Tyler Parkway detour and the Cannonball River Bridge listing both run through Nov. 27. Memorial Highway work resumes in 2027, rebuilding the stretch from Riverwood Avenue SE to 32nd Avenue SE, according to NDDOT. Mandan lists an 8th Avenue and 27th Street NW reconstruction for 2027 on its projects page.

For live state highway and interstate conditions, check ND Roads or call 511. For city streets and county roads, check with the City of Bismarck and its closure map, the City of Mandan, the Burleigh County Highway Department or the Morton County Highway Department at 701-667-3346.