Protests of Wyoming's December federal lease sale are due today. The City of Umatilla has declared an emergency over Oregon's pause on data center permits. And water users in two Yellowstone basins have Water Court deadlines coming up.
Oregon
The Umatilla City Council declared an emergency on Oct. 20, citing "the threat of widespread financial loss" from new data center developments being put on hold, OPB reported. City staff estimate the city will lose more than $2.5 million a year in tax payments and $12 million in planned water infrastructure work. In an email, Hermiston City Manager Mark Morgan estimated the cost to Hermiston residents at about $550 million in lost future local fee revenue, without giving a time period. Morrow County Commissioner Gus Peterson called the pause "executive overreach."
Gov. Tina Kotek's Oct. 9 letter directs the Department of Environmental Quality to pause "processing and issuance" of air and water discharge permits for new or expanded data centers until July 1, 2027. It also pauses DEQ's processing of city requests to renew or modify wastewater treatment plant permits to take data center discharge. The letter says the pause will last "until we can assure Oregonians that our laws will adequately protect our communities and the environment of our state." Kotek and her Republican opponent, state Sen. Christine Drazan, both say they favor a moratorium on data centers, according to OPB.
Amazon Web Services, which runs more than a dozen data centers in Morrow and Umatilla counties, objected. Shannon Kellogg, an AWS vice president for public policy, said the directive came "without meaningful stakeholder engagement." Oregon Rural Action obtained and shared the letter, and its policy director, Kaleb Lay, said the state needs new laws on data centers' water and electricity use, transparency, and nondisclosure agreements. The Legislature convenes in January and is expected to take up data center bills.
The state Energy Facility Siting Council meets Nov. 19 and 20. The Oregon Department of Energy expects to bring the council its recommendation on the termination request for the Boardman Coal Plant site in Morrow County, and will likely bring two rule changes on compliance and carbon offset payments, according to the department's project updates. Public comment on both rules closed Sept. 25. The department also plans to issue a draft final order in November on an amendment to the Wheatridge Renewable Energy Facility East, also in Morrow County. Meeting details are on the council's meetings page.
Wyoming
Protests of the Bureau of Land Management's Dec. 9 Wyoming oil and gas lease sale are due today, Wednesday, Oct. 28. The sale offers 172 parcels covering 249,573 acres and will be held online through Efficient Markets, BLM said. Parcel maps and protest instructions are on BLM's ePlanning page for the fourth-quarter sale.
Montana and the Dakotas
BLM's Montana-Dakotas office held an online sale of 20 parcels in Montana and North Dakota, totaling 3,388 acres, on Tuesday, Oct. 27, according to its August notice. Results were not yet posted Wednesday; they will be in next week's edition. Next up is a January 2027 sale of as many as 60 parcels covering 18,565 acres. Its scoping period closed Sept. 24. If BLM follows the steps it used for the October sale, it will next open a 30-day public comment period on the parcels and its environmental review, then issue a sale notice and open a protest period.
The Montana Board of Oil and Gas Conservation holds its next hearing Thursday, Dec. 10, at 9 a.m. in its Billings hearing room, 2535 St. Johns Ave., with a business meeting the day before at 2 p.m. Applications for that hearing are due by noon Thursday, Nov. 5, according to the board. The docket will post on the board's dockets and orders page.
Two Montana Water Court deadlines are coming in the Yellowstone River system. Objections to the interlocutory decree for Basin 43D, the Clarks Fork of the Yellowstone, are due Nov. 23; that decree covers 597 water right claims, according to the court's notice. Objections for Basin 43Q, the Yellowstone between the Clarks Fork and the Bighorn, are due Dec. 22 and cover 836 claims, according to the court's notice. Objections must be filed on Water Court forms and received by the Montana Water Court, PO Box 1389, Bozeman, MT 59771.
Further out
The Forest Service is preparing an environmental impact statement for Rare Element Resources' Bear Lodge rare earth mine, proposed on the Black Hills National Forest in northeast Wyoming. The project is a "covered project" under FAST-41, a federal law meant to speed permitting. Scoping comments closed Aug. 28, and that was the only comment window the agency described: it "will not publish a draft environmental impact statement or conduct an objections process," and expects to publish the complete statement in late 2027, according to its Federal Register notice.