# City of Bismarck approves a Renaissance Zone tax exemption, and Mandan planners back a 145-lot subdivision
- URL: https://www.bunchgrass.org/city-of-bismarck-approves-a-renaissance-zone-tax-exemption-and-mandan-planners-back-a-145-lot-subdivision/
- Published: 2026-11-28T16:33:13.000Z
- Updated: 2026-11-28T16:33:13.000Z
- Description: The Bismarck City Commission approved a Renaissance Zone tax exemption 3-2, dropped three protested street lighting units and let staff seek groups to run a low-barrier shelter, and Mandan planners recommended a 145-lot south side subdivision.
- Author: Bunchgrass Staff
- Tags: Missouri Slope, #wrap-up

The Bismarck City Commission on Tuesday voted 3-2 to approve a Renaissance Zone property and income tax exemption for a new office and warehouse on East Front Avenue, dropped three proposed street lighting units in existing neighborhoods after protests, and agreed to seek expressions of interest from groups that might run a low-barrier emergency shelter. In Mandan, the Planning and Zoning Commission on Monday recommended a 145-lot subdivision and annexation on the city's south side. The outcome of a battery storage permit on the Morton County Commission's Tuesday agenda had not been reported by Friday.

## Morton County

### Morton County Commission

The commission met Tuesday, Nov. 24, with a request from Minnesota Power for a special use permit for the Bison Battery Energy Storage System, a 325-megawatt project beside the company's Bison Wind Energy substation, on its [agenda](https://mortonnd.gov/uploads/dm/93914/11.%5FNovember%5F24%5F2026%5FAgenda.pdf?ref=bunchgrass.org), along with amendments to the county Land Use Code that would add the county's first rules for battery storage facilities. The county Planning and Zoning Commission had recommended approval of both, according to the [meeting packet](https://mortonnd.gov/uploads/dm/93916/November%5F24%5F2026%5FPacket?ref=bunchgrass.org). The outcome of either item had not been reported by Friday ([meeting video](https://dakotamediaaccess.org/programs/show/morton-commission-replay-11-24-26-2-11972/?ref=bunchgrass.org)).

### Mandan Planning and Zoning Commission

By a 10-0 roll call vote on Monday, Nov. 23, the commission recommended that the City Commission approve the preliminary plat, zone change and annexation for Keidel's South Heart Terrace 5th Addition, contingent on the City Commission approving the annexation ([agenda and packet](https://mandannd.portal.civicclerk.com/event/782/files?ref=bunchgrass.org); [meeting video](https://dakotamediaaccess.org/programs/show/mandan-planning-zoning-replay-11-23-26-2-12132/?ref=bunchgrass.org)). The plat covers 69.41 acres south of 19th Street West and east of Highway 6 and would create 145 lots in seven blocks, one of them a drainage lot. Most would be zoned R7 for single-family homes, with a group of R3.2 lots that allow duplexes and four RM multifamily lots on the west side. The eastern part of the land is outside city limits and zoned agricultural, which is why annexation is part of the request.

Rachel LaQua of Interstate Engineering, the city's interim planner, said an earlier version had been recommended for denial and that staff had been concerned about connections east to the planned Clover Grove subdivision and secondary access for fire and emergency vehicles. The new plat adds Inspiration Drive, which winds through a coulee to connect with First Avenue and Clover Grove. LaQua said one lot still lacks enough road frontage and must be fixed at the final plat stage, when the city will expect grading, stormwater, water and sewer plans and a development agreement. The city received one written comment, which raised concerns about the multifamily zoning.

The project's surveyor said Eighth Avenue Southwest was shifted east so lots could be built on both sides of it. A real estate agent working with the developer said the R3.2 homes would be designed to look like single-family houses with basement units that could be rented, and that the developer's covenants would require them to be owner-occupied.

The commission also approved its 2027 meeting schedule, generally the fourth Monday of each month, and kept Monday, Dec. 28, for its next meeting, when it will make term appointments and a new city planner is expected to attend.

Coming up: The Mandan City Commission will consider a resolution establishing a new home tax exemption and a property tax exemption application from Netri Hospitality LLC for improvements to commercial and residential buildings at 5:30 p.m. Tuesday, Dec. 1, at City Hall, 205 Second Ave. NW ([preliminary agenda](https://mandannd.portal.civicclerk.com/event/347/files?ref=bunchgrass.org)). On Tuesday, Dec. 15, Mandan voters decide a citizen-initiated ordinance that would prohibit large-scale and multiple data centers with 25 megawatts or more of electrical capacity or combined demand in the city and certain territory under its zoning authority. Voting runs from 7 a.m. to 7 p.m. at Spirit of Life Roman Catholic Church, 801 First St. SE, according to the city's [elections page](https://www.cityofmandan.com/elections?ref=bunchgrass.org), which says there is no early voting.

## Bismarck and Burleigh County

### Bismarck City Commission

All five commissioners attended the Tuesday, Nov. 24, meeting ([agenda and packet](https://bismarcknd.portal.civicclerk.com/event/2138/files?ref=bunchgrass.org); [meeting video](https://dakotamediaaccess.org/programs/show/bismarck-city-commission-replay-11-24-26-2-11854/?ref=bunchgrass.org)).

Renaissance Zone. By 3-2, the commission approved JLK Properties LLC's new construction Renaissance Zone project at 1216 E. Front Ave., an office and equipment warehouse for All Seasons Outdoor, a snow removal and irrigation company. The approval exempts the value of the new building from local property tax for five years and exempts income from the location from state income tax for five years. Commissioners Matt Hull, John Risch and Amelia Doll voted yes; Commissioner Michael Connelly and Mayor Michael Schmitz voted no. Planning staff put the project cost at about $1.53 million, or about $235 a square foot, above the program's $150 minimum for new commercial construction, and estimated the five-year benefits at $100,000 in property tax and $12,500 in income tax. The Renaissance Zone Authority had recommended treating the project as full new construction, with a baseline building value of $0 rather than the roughly $73,000 value of a building on the site that was demolished this year. Connelly said the project did not meet the standard he usually applies to such requests, and Schmitz said the project was outside the area where he considers the program appropriate.

Street lighting. By 5-0, the commission found protests insufficient to stop units 1 through 5 of Street Improvement District SI 606, new street lighting paid by special assessments, and dropped units 6, 7 and 8, all in existing neighborhoods: Columbia Drive and Lansing Lane off South Seventh Street, Crescent Lane off Parkview Drive, and North Fourth Street from Lunar Lane to Nova Drive. City Engineer Gabe Schell said units 6 and 8 had drawn enough protests to stop them, while protests on unit 7 covered 45% of the area, short of the 50% threshold. He said two more protests, one filed after the deadline and one unsigned, would have pushed it past the threshold, and recommended honoring them.

Shelter. Bismarck-Burleigh Public Health Director Renae Moch said staff found few city-owned properties that could house a low-barrier emergency shelter, none available for immediate occupancy, and that none of the privately owned sites visited with the city building official and fire marshal met every need. She said planning assumes 80 to 100 people in 8,000 to 10,000 square feet, and cited the January 2026 point-in-time count of 81 people unsheltered and 134 in emergency shelter or transitional housing. Commissioners agreed by consensus, without a roll call vote, to let staff issue a request for expressions of interest from possible operators and other partners. Moch's draft timeline would post it Dec. 7 with responses due Jan. 8 and a report Jan. 26; commissioners left room for staff to extend it into February.

Police headquarters. Police Chief Jason Stugelmeyer and representatives of the design firm JLG said the project remains within the $97.6 million budget the commission approved in May, about $83 million of it for construction. The first bid package goes out in late January, construction is set to start May 1, and the construction manager expects about 22 months of work. No action was taken.

On the consent agenda, approved 5-0, commissioners approved the preliminary plat for First Responders Fourth Addition and called a public hearing on Ordinance 6689 to annex part of it, awarded 2027 water and wastewater treatment chemical bids, and approved $11,885 in change orders on the Boulder Ridge storm sewer project. Two police donations were pulled from the consent agenda and approved 5-0, including $111,000 from Martha Trussell to buy a police dog and a K-9 vehicle.

Coming up: The Bismarck City Commission will consider awarding bids for SI 606 street lighting units 1 through 5 at 5:15 p.m. Tuesday, Dec. 15, under the city engineer's schedule, in the Tom Baker Meeting Room, City/County Office Building, 221 N. Fifth St. The Burleigh County Commission did not meet this week; its next regular meeting is at 5 p.m. Monday, Dec. 7, in the same room, according to its [meeting schedule](https://www.burleigh.gov/government/county-commission/schedule/?ref=bunchgrass.org).